Standardization of Definitions for Benchmarking- Zoltan W. Lukacs, P. Eng.
Dedication
This report is dedicated to the memory of Ian Muirhead, who at the time of his
untimely passing was Director of the Department of Mining and Petroleum Engineering
at the University of Alberta. Ian understood Industry’s need to conduct this study,
and provided the inertia to get the project off the ground.
Credit goes out to Blair Tuck, whose research for his Masters Project formed the
basis for the conclusions reached within this report.
Credit is also extended to Chris Barclay of Luscar Ltd, and Denise Duncan from Syncrude
Canada Ltd. , who as members of the industry steering committee for the project
provided the initial direction and assistance in conducting the surveys.
Executive Summary
The desire to engage in collaborative relationships to gain competitive advantage
at a global level was the driver for a proposal by the Surface Mining Association
for Research and Technology (SMART) to commission a research project intended to
enable comparison of equipment performance across the mining industry.
As a start point it was decided to focus on the development of common definitions
for availability and utilization. A UOA grad student in fulfillment of a Masters
degree project requirement conducted a survey of twenty-five mining operations in
Canada and the United States. A methodology was developed to capture industry practice
and classify the responses. Several typical operating events encountered in the
normal operation of a mine were identified and included in the survey for each operation
to classify.
The survey found that the formulas and definitions for availability and utilization
parameters were similar, however differences in the meanings behind the formulae
and the classification of events occurring in the course of the operation of a mine
created inconsistencies in reporting. While it is possible to derive common definitions
for operating parameters, comparison is meaningless without addressing the discrepancies
occurring at a more fundamental level of classification of operating events into
time categories.
With this finding, the project objectives shifted to identify the fundamental differences
between the way operations classified normal operating events. The results are summarized
in the report.
As the operations surveyed were understandably reluctant to change their formulas
or data collection practice, a system which uses existing data collection infrastructure
to develop a parallel benchmarking database solution has been proposed for operations
wishing to participate in a benchmarking initiative. A central database is proposed
where participants in the study would have access to the accumulated data allowing
comparison using either of their own formulas and definitions, thereby allowing
comparison to historical data, or to standardized benchmarking formula developed
for the purpose of industry wide comparison. The benchmarking definitions derived
for this purpose would be the first step toward development of an industry standard
for selected operating measures.
A portion of the survey was dedicated to determine the extent to which maintenance
performance parameters were used, and if interest exists in benchmarking maintenance
performance. Most operations recognize the need to improve maintenance processes
and performance management systems, and are actively working toward this end. There
appears to be little collaborative effort in this area, as a result most operations
seem to be "reinventing the wheel". As there is interest in pursuing some form of
maintenance information sharing, a study comparing maintenance practice and the
development of performance standards for maintenance would be of value to the mining
industry.
Background
The motivation for this study was to enhance the collective efficiency of the Canadian
mining industry by enabling sharing of information on operating performance.
Benchmarking has become one of the methods by which mining companies across North
America are attempting to improve their fleet operations and maintenance practice.
This follows the success of benchmarking initiatives in other industries.
Some of the benchmarking applications identified within the mining industry includes:
- Comparison of performance within similar environments and equipment, for the purpose
of assessing performance capabilities and setting targets.
- Identification of industry best practices.
- Helping in equipment purchase decisions by understanding the capability of equipment
in like applications, and,
- Combining information to help provide a common industry voice to communicate with
equipment vendors
One success story in mining industry collaboration is the Large Tire User Group.
Under the auspices of Surface Mining Association for Research and Technology (SMART),
the Large Tire User Group established a multi-company, large tire database, which
was successful in establishing consumption information, sharing of large tire testing
data, and the sharing of procedures for tire and rim maintenance.
Despite its benefits, the mining industry in general has lagged other industries
in the adoption of benchmarking. Some of the barriers limiting the application of
benchmarking are:
- A reluctance to share information due to confidentiality and privacy concerns;
there is a particular sensitivity when cost data is concerned.
- Resources to dedicate to benchmarking initiatives (time);
- Lack of commitment and support through all levels of the organization.
- Lack of consistent, relevant performance indicators.
The results of previous benchmarking relationships have been mixed, as comparison
between operations was complicated by inconsistencies in the interpretation and
reporting of data between operations.
In response to industry interest to develop meaningful indicators with which comparison
was possible, SMART commissioned a project to develop a proposal for standardized
performance indicators through the University of Alberta.
This paper outlines the project methodology, summarizes the results of a survey
of industry practice, and presents a proposal to advance the project to the next
stage.
Project
The project was initiated in January of 1998. Project participants, members of SMART,
provided funding for the initial phase.
Project Sponsors were;
- Fording Coal Ltd
- Iron Ore Company of Canada
- Manalta Coal (Luscar)
- School of Mining and Petroleum Engineering
- Suncor Energy
- Syncrude Canada Limited
- TransAlta Utilities
The project was coordinated through the University of Alberta, the research forming
the basis for a graduate level thesis. A steering committee was formed among the
project participants to direct the project.
The project was to be carried out in three phases;
- Phase 1 - survey current definitions and practice, and develop recommendations
for the standards and definitions for benchmarking parameters.
- Phase 2 - perform the data collection for benchmarking comparisons.
- Phase 3 - develop and maintain a database to enable the exchange of benchmarked
information between contributing operations.
The second and third phases were contingent on successful execution of Phase 1,
which requires the acceptance of proposed standard reporting definitions.
This report summarizes the conclusions of Phase 1, the survey of current practice,
and provides recommendations to enable action toward phases 2 and 3.
The survey consisted of three sections;
- Definitions of the common performance indicators;
- Classification of typical operating events or occurrences at each operation;
- questions relating to maintenance performance indicators to determine the extent
to which maintenance performance indicators are used within the industry, and to
gauge interest in maintenance benchmarking.
The first stage of data collection took place in late February and early March of
1998. This stage consisted of site visits to eight surface mines, allowing participants
elaborate on responses.
The original survey was revised for a mail survey, sent to forty-four large surface
mines in Canada and another fifty-five in the United States. Seventeen more responses
were received for a total of twenty-five.
Results
For illustrative purposes, the flow of information from which the performance definitions
are derived is reflected in Figure 1. During the course of a day various planned
and unplanned events occur. These events are recorded either manually or
electronically through an automated data collection system. Based on established
rules and guidelines developed over the history of the operation, these events are
coded to defined time classifications, again either manually or electronically.
These classifications are for the most part are common to the mining industry, and
make up the terms of the definitions of the performance measures used in
the industry.
Figure 1 Performance Reporting Information Flow
The survey initially focussed on definitions of availability and utilization used
by industry. The general intent of the definitions was the same; ie how many hours
are available to the operation. Availability formulas generally represented a ratio
of equipment hours available to the operation, to total hours. While there appeared
to be consensus on the definitions of availability, inconsistencies in the allocation
of events to time classifications diminished the validity of any comparison of operating
parameters.
In most cases total hours consisted of scheduled hours (or a sum of operating, delay,
standby, and down hours) or calendar hours.
One of the differences encountered was in the use of mechanical or physical availability;
the majority of operations using mechanical availability. Six of the surveyed operations
use both physical and mechanical availability, however, some of the operations using
a mechanical availability exclusively, defined mechanical availability in terms
similar to physical availability at other mines.
The other significant difference was in the use of the term "operating hour". Several
operations made the distinction between net, or a "pure" operating hour vs a gross
operating hour, which includes operating delay. Of the respondents using the term
"operating hour" only, the meanings varied from a pure operating hour (similar to
a net operating hour), to an operating hour which includes delay.
The most significant difference between operations that affects the ability to compare
results, is the allocation of events to the time classifications terms making up
the formulas. For example operations comparing on the basis of mechanical availability,
which excludes standby or idle time, may be affected by differences that occur between
what is considered operating delay and standby time at the individual operations.
The inclusion of planned downtime in idle or standby time results in different availability
than operations that consider planned outages as scheduled outage.
Utilization related parameters resulted in even greater variation in application
and intent. The general intent of utilization parameters was to measure the use
of the equipment, in some cases against available time and in others against total
time. The basic formulas were also found to be quite similar for utilization parameters,
however there was a large variation in terminology, from utilization, to use of
availability, effective utilization, and operating efficiency. Many of these terms
were used interchangeably by survey participants to reflect the same measure. As
an example, the same formula was used to describe "Utilization" and "Overall Efficiency"
at different operations, however the definition of the NOH term used in the two
formulas was different.
Utilization measures as well are influenced by the classification of events to standby
vs. operating delay, and nonscheduled time vs. standby time.
In order to enable comparison between operations, discrepancies would have to be
addressed at a more fundamental level, specifically the allocation of operating
events (such as lunch breaks, fuelling, queuing) to commonly accepted time classifications
(such as operating hours, operating delay, standby, down, etc.).
In order to identify the differences between the way operations classify typical
events the Table 1 was developed to reflect the major time classifications used
within the mining industry.
All events encountered in the course of operating a mine would fall into one of
the time classifications. Table 2 is a summary of the classification by the survey
participants of some of the most common events.

Table
1.
Total Hours
Total hours is not used as a classification for this study, however because it is
used by many of the operations participating in the study, its relationship to the
other parameters is noted.
The definition of total hours varied depending on how the operation classified scheduled
outages.
Where scheduled outages were part of the operation, total hours were generally equal
to scheduled hours, defined as calendar hours, less scheduled outages. Where there
were no scheduled outages, or in cases where scheduled outages were considered part
of operating or standby time, total time equated to Calendar hours.
Calendar Hours
Calendar hours varied depending on the operation. Twenty-two respondents defined
calendar hours as 8760 hours per year. One operation removed statutory holidays,
and defined the year as 8520 hours. Another removed hours allocated to replacing
a manufacturer defect from calendar hours. Comparisons affected by statutory holidays
should be viewed with caution as not all provinces and states have the same statutory
holidays.
Scheduled Outages
In most cases scheduled outages when used, included statutory holidays, planned
shutdowns and scheduled down shifts. Scheduled outages were in some instances used
to capture unforeseen events, which are not easily classified into the normal operating
classifications. These included events such as major weather related outages, Acts
of God, and labour disruption.
Scheduled hours are calculated as the difference between calendar and scheduled
outage.
Almost half the mines surveyed did not classify scheduled outage separately. Of
those, planned shutdowns and scheduled downshifts were classified as idle or standby.
This difference affects the calculated standby time.
Down Time
The distinction between down and available was quite clear throughout. In most cases
the unit was mechanically operable or it was not. Opportune maintenance or maintenance
taking place during planned shutdowns was in almost all cases classified as down
time.
In the majority of operations surveyed, consumables changes (ground engaging tools,
hoist ropes etc.) were considered part of down time, regardless of whether mechanics
or operations were involved in the change.
Available hours were then calculated as the difference between Total or scheduled
hours less down time.
Idle (or Standby – these terms were used interchangeably)
Idle or standby time was in most cases considered the time the equipment was available,
but not manned or used.
The major discrepancies affecting idle time were the classification of planned outages
as discussed above, safety and crew meetings, which were equally defined as operating
delay, and to a lesser extent lunch breaks and power outages.
Table 2. Summary of Event Classifications
Operating hours
The majority of discrepancies occurred in the definition of operating hours, and
the allocation of events between operating delay, Gross Operating Hours, and Net
Operating Hours. Several operations had one classification, Operating Hours. In
some cases Operating Hours incorporated delay, reflecting the entire time the unit
operated, while in others, Operating Hours referred strictly to the time the unit
was producing.
Gross Operating Hours were generally calculated as Available hours less idle
or standby time. GOH was generally defined as operating time plus operating delay.
Net Operating hours, also referred to as operating time, or production hours,
is the difference between GOH and operating delay.
Operating Delay, generally referred to activity where the unit was available
and manned, but not involved in production.
Working hours was a term used by a number of mines, also with multiple meaning;
at one operation it equated to a GOH definition, while at another the definition
reflected a Net Operating Hour.
One of the major areas of disagreement is in the classification of queue time as
delay or operating time. It was found that operations with manual time and data
collection tended to incorporate queuing as operating time to an upper limit, where
it was then classed as delay. Operations with automated data collection systems
where more likely to classify any queuing as delay. Further discrepancies resulted
from the definition of a queue. In some cases if truck waiting was caused by shovel
repositioning or face cleanup, it was not defined as queue, or the delay was not
considered a queue until more than one truck was waiting. These discrepancies came
to light after the surveys were completed, and were not further addressed.
Maintenance Survey
The most common maintenance indicator is mechanical availability, while some use
reliability to varying degrees. Other indicators include; maintenance ratio (maintenance
hours to operating hours); Cost per Hour; Backlog and PM compliance.
All operations have maintenance management systems, though some are limited to work
order generation and history. Retrieval of historical information has been raised
as an issue at some operations.
All operations keep component histories, however in most cases the history is limited
to hours at replacement. Half the operations surveyed keep a failure history, though
in most cases this is simply failure cause. Two respondents indicated they kept
records of failure analysis on major components, or accidents.
Component changeouts were based on operating hours or depending on the component,
service meter hours. Condition monitoring was used to varying degrees by all respondents.
Most commonly used condition monitoring methods included oil sampling, vibration
analysis, visual inspections, gear inspections, and thermography.
Some operations were either in the process of moving towards a function or usage
based metric for replacement as an alternative to hours, or strongly considering
it. Examples include tonne – km for tires, tonnes for hoist ropes, or BCM on buckets.
About half had some form of downtime analysis, most relating to distribution of
downtime by equipment component or system. About a third documented maintenance
time by activity, ie wait labour, wait shop space, cleaning, Preventive, breakdown,
warranty etc.
The majority expressed interest in some form of maintenance information sharing,
although many were not sure what form it should take. Interest was expressed in
sharing in component histories or common equipment problems.
Conclusions
1. Any comparison is meaningless due to the lack of consistency in the way in which
operating events are classified. Until this is resolved there is limited value in
proposing common definitions for availability and utilization.
The focus moving ahead must then be on the consistent allocation of operating events
to agreed on time classifications.
2. The consensus through the survey interviews was that there is strong interest
in information sharing and comparison, however none of the operations felt they
would be willing to adopt new definitions for operating parameters or adopt new
standards for allocation of operating events in order to enable information exchange.
To enable comparison of data, information sharing must take place in such away that
existing operating data collection and reporting systems at individual mines can
operate unaffected, and that access to historical data is protected.
To accomplish these constraints, a solution that utilizes the data storage and manipulation
capability of existing data collection systems could be implemented.
3. There is interest in pursuing some form of maintenance information sharing. Most
operations recognize the need to improve maintenance management systems and processes.
The development of maintenance performance management systems lags that of other
production tracking systems in mining. There appears to be little collaborative
effort in this area, as a result most operations seem to be "reinventing the wheel".
A study comparing maintenance practice and the development of performance standards
for maintenance would be of value to the mining industry.
4. Once a benchmarking data collection infrastructure is established, other applications
could benefit. Some of these include:
- The Large Tire User Group, which requires data common to this initiative;
- The data management infrastructure could be used to improve reporting parameters
specific to OEM availability guaranty reporting.
- Loss Control system benchmarking.
- It was also suggested that the structure developed for this initiative could form
the framework for other web based collaborative initiatives such as purchasing.
Path forward
A decision to proceed is required; the benefits must be weighed against the resources
needed to establish the benchmarking infrastructure, as well as the ongoing upkeep
of the system. The value in the initiative will be realized by the ongoing participation
of several operations.
The path forward is to develop a process which makes use of existing data management
systems to collect data on operating events, and establish the infrastructure to
collect event based data from participating operations to an independent, central
benchmarking data warehouse. The proposed data management structure is reflected
in Figure 2. Participating operations will have access to the data at a high level,
which can either be reported in the definitions agreed to by a benchmarking steering
committee, or inserted into their own formulas, to enable comparison with their
own historical data. The definitions developed for the purpose of comparison will
represent a "straw dog" for industry wide standardization. Participants will not
be obligated to adopt the proposed standards, as they will have access to the database
data. The development requirements and costs of the proposal are summarized in Figure
3 and Tables 3 and 4 .
For the initiative to advance, the following actions are recommended;
- Identify project manager to coordinate system design, help establish rules for
allocation of events within the benchmarking database, incorporate standardized
reporting parameters, and coordinate efforts at participating mines.
- Identify interested participants; establish steering committee from participating
operations to confirm guidelines for system development, agree on assignment of
events to time classifications, and approve standard formulas proposed for reporting
key performance parameters
- Determine if system would facilitate Large Tire User Group information data collection.
Coordinate development to ensure system accommodates their needs.
- Agree on location of benchmarking data warehouse. The initial proposal was to
establish central data store at the University of Alberta School of Mining. Another
option is to develop a database accessed through the SMART website. The location
of the database may have an impact on who will maintain the database on an ongoing
basis.
- Initiate design and coordinate database modifications with dispatch system vendors,
or onsite support.
- Establish if interest exists for a similar study relating to maintenance practice
and performance measures.
Table 3 System Development Requirements
SMART/Steering Committee
- Agree on event allocations (to time classifications)
- Agree on Definitions of Operating Parameters for reporting
(ie Availability and Utilization)
- Database content and reporting requirements
Participants
- Develop translation Tables for event allocation (1 Day)
- Create alternate benchmark data files and ASCII data file formats for transfer
(3 Days)
Data Administrator
- Develop Database and Report Formats (20 days minimum)
Ongoing Support Requirements
- Initial (3-4 months) 5 Days/month
Table 4 Cost Estimate
Development Cost
Participant Direct (40 hrs @ $100/hr) $ 4,000
Data Infrastructure (160 hrs @ $100/hr) $ 16,000
Implementation Cost (40 hrs @ $100/hr) $ 4,000
(distributed between participants) $ 20,000
Support Costs ( distributed between participants)
Initial (40 hrs @ $35/hr) $ 1,400/ month
Ongoing (16 hrs @ $35/hr) $ 560/ month
(Estimates assume contract labour; any in-kind support by participants will reduce
cost)